Project Mustang STY 1A
- Industry
- Location
- McCarran, NV
- Total SF
- 300,000
- Tonnage
- 8,700
With expertise in mechanical and electrical support steel, we played a crucial role in the construction of Project Mustang STY 1A. Using pre-engineered metal building (PEMB) steel, we deployed multiple crews on an accelerated schedule to ensure timely completion and seamless integration with the data center campus.
Type
New Construction
General Contractor
Holder Construction
Purpose
Mechanical, electrical support steel on dry coolers to support data center campus. PEMB steel. Multiple crews on an accelerated schedule
Construction
2019-2021